Pipeline in Peril
by Richard A. Fineberg
As it enters its 22nd year of operation, the 800-mile Trans-Alaska Pipeline
poses a growing risk to Alaska's inland environment. Carrying more oil than any
other pipeline in the US, the Trans-Alaska Pipeline (TAPS) pumps 1,500,000
barrels of North Slope oil to Port Valdez every day.
The pipeline is operated by the Alyeska Pipeline Service Co., a wholly-
owned subsidiary of seven oil companies. ARCO, BP and Exxon own more than 90
percent of Alyeska and control more than 90 percent of North Slope's oil
extraction.
TAPS traverses the flat North Slope to enter the Brooks Range, where it
climbs from sea level to crest Atigun Pass. From there, the pipeline descends to
cross the wide Yukon River. For its final 350 miles, TAPS mounts the Alaska
Range, descending and climbing again to 2,788 feet to top Thompson Pass before
plunging through Keystone Canyon toward the terminal at Valdez .
The oil, heated to roughly 116 degrees Fahrenheit, is pushed south at 5
mph by ten pump stations powered by powerful jet engines that consume 50,000
gallons of fuel a day. The journey from the North Slope to the 18 giant storage
tanks at Valdez takes six days.
Virtually every element of pipeline operations is controlled from the
Operations Control Center (OCC) at Valdez. The OCC directs crews at the
pipeline's remote pump station who strive to maintain oil flow and regulate
pipeline pressure by opening and closing gate valves and moving oil to and from
relief tanks.
Picture TAPS as an animal with ten distant hearts - the mainline pumping
stations. The brain of this animal is a computer called an MV 20000, which
monitors a constant flow of information from the pipeline. This information
helps the OCC operators to issue appropriate orders to the pump stations and 62
remote control gate valves (RGVs) along the 800-mile line.
The OCC communicates with pipeline workers, pump stations and RGVs via 42
microwave relay stations that Alyeska calls the Backbone Communications System.
Each pumpstation has a control room operator who manipulates the big
mainline pumps, valves, relief tanks and booster and injection pumps. In an
emergency, pumpstation personnel can assume direct control of operations.
TAPS crosses 34 rivers and more than 700 smaller streams comprising three
major watersheds that drain into two oceans and one sea. Excess oil pressure
could rupture the pipe and cause a spill. An inland spill would endanger both
the spectacular scenery and the diverse fish and wildlife habitat that is home
to moose; caribou; polar, black and grizzly bears; Dall sheep; wolves,
wolverines, foxes, lynxes, ptarmigans, grouse, waterfowl and peregrine falcons.
Fish at risk from an inland spill include shellfish, grayling, Arctic char,
pike, whitefish, lake trout and four species of salmon.
Under normal conditions, Alyeska's Operations Control Center (OCC) at
Valdez directs crews at the pipeline's remote pump station who strive to
maintain oil flow and regulate pipeline pressure by opening and closing gate
valves and moving oil to and from relief tanks. Pump crews also start and stop
pumps and inspect the line and report conditions to OCC headquarters.
To stop a spill in progress or to make preventive repairs, Alyeska's only
option is to shut down the line.
When Gate Valves Fail
TAPS oil flow is controlled by 151 valves strategically located along the line
including: 62 remote control gate valves (RGVs) located immediately upstream of
major river crossings and other environmentally sensitive areas, 80 check valves
hinged clappers that close automatically in response to back pressure,
preventing back flow on uphill slopes when the line is not forcing oil toward
Valdez. There are also nine manually operated gate valves used for maintenance.
The RGVs use giant paddle-shaped steel slabs that straddle the pipeline to
stop the flow of oil. In open position, a 48-inch-diameter hole in the slab
allows oil to continue south. The solid portion of the slab rests above the
pipe. On command, a gear forces the giant steel slab down, cutting off
pipeline's flow.
The RGVs were originally designed to close in four minutes, limiting
drainage after closure to an average of 13,000 barrels, with a maximum spill of
50,000 barrels. The RGVs also permit "staged shutdowns" that prevent over-
pressuring of the pipe due to emergency closure.
In order to respond to leaks on the pipeline, it is first necessary to
detect them. In 1991, GAO observed that pipeline monitors had never tested the
leak detection system to ensure that it worked. In late 1995, the leak detection
system approached the accuracy Alyeska promised in 1971 - but only during
periods when the pipeline was stable enough to permit accurate calibration of
the various inputs required for accurate measurement. In 1995, those conditions
occurred for a total of approximately one day out of 30.
When dealing with such huge quantities of oil, relatively small leaks can
be serious. A spill of just 0.001 percent of TAPS' daily flow would cover an
entire football field with a layer of crude oil more than two inches deep.
Alyeska's 1977 boast that "no spill is likely to flow unnoticed for more
than a few minutes" was discredited two years later by the Atigun Pass spill,
estimated at between 1,500 and 5,000 barrels. That spill continued for two to
four days without triggering an alarm at Valdez.
In 1991, a new, more powerful computer was installed but testing revealed
that the system could not detect an 800 barrel per day (bpd) leak: It took six
hours to identify a 3,500 bpd leak. During a three-month review in 1993-94, the
leak detection system issued false alarms on the average of eight times a
month.In November 1995, the system was set to alarm only for spills larger than
3,000 bpd 42 percent of the time.
Alyeska Closes Pump Stations
As shutdowns cause Alyeska and its parent companies to lose money, their
increased frequency serves as a warning flag that something is seriously amiss.
For TAPS' first 18 years, Alyeska listed only 60 shutdowns. In 1994 (after
congressional criticism called public attention to a variety of mechanical
problems), Alyeska instituted a new policy requiring a shutdown whenever the OCC
loses touch with critical line equipment for more than two minutes.
In 1994 and 1995, the shutdown rate exceeded eight per year. Increased
communication failures and corresponding shutdowns may indicate the risks
associated with operating an aging pipeline.
In January 1997, Alyeska announced plans to move its field operations
headquarters from Anchorage to Fairbanks and Valdez, a tacit recognition that
the existing organization lacked effective control of the pipeline.
Alyeska's consistent efforts to cut costs and personnel is an additional
factor in pipeline safety. Alyeska is in the process of reducing its base
operating costs (exclusive of "fix-up" expenses) from $581 million in 1994 to
$409 million in 1999. Large cuts are being made to both the Alyeska work force
and the work force of its contractors. Alyeska reduced its staff from 1,352
people in October 1994 to 1,053 by the end of 1995, with a target of 839
employees in 1999.
These cuts are particularly disturbing in view of the audit observation
that it was often the expertise and dedication of veteran Alyeska employees that
saved the poorly maintained pipeline from disaster. A well-known cost advantage
of downsizing is to replace senior staff with lower-paid, less experienced
personnel. Alyeska officials maintain that they would never jeopardize safety or
the environment to save money, but the conflict between these two goals is
inevitable.
In the interest of economy, Alyeska decided to close Pump Stations 8 and
10 in the summer of 1996, bringing pump Station 7 back on line. If throughput
decline continues, Pump Stations 2 and 6 will be shut down in 1997. Pipeline
workers who are not scheduled for lay off say they are concerned about how
Alyeska will handle a broad range of problems.
Ramp down plans call for the increased use of Drag Reducing Agency (DRA),
an additive inserted into the line to make oil easier to pump. As Alyeska
removes pump stations from action, the company will use more DRA to enable
remaining pumps to push the oil south. In 1995, approximately 414,000 gallons
were injected into the pipeline.
DRA is a hazardous kerosene-based polymer whose chemical composition is a
trade secret. In the pipe, DRA tends to coat the probes that measure the oil
flow. When DRA is present, the leak detection systems have an even more
difficult time interpreting the data they receive. Operators in Valdez describe
the effects of DRA as "spooky."
Problems at Pump Station #9
During an April 1994 maintenance shutdown, a key unit at Pump Station 4 that
controls remote gate valves (RGVs) failed. When the faulty control unit was
replaced, valves still failed to respond because wiring had grown brittle with
age.
After a planned, line-wide maintenance shutdown in September 1995, staff
at Pump Station # 9 were waiting for OCC's order to resume pumping. It was just
past midnight when the station operator told the "rover" (the assistant who
checks the equipment at the facility) to expect an order from Valdez to start up
one of the big jet turbines that powers the pumps.
A rapid pressure build-up preceding the arrival of the oil flow caused the
yard-check (a pressure-driven one-way valve normally closed to prevent back
flow) to slam repeatedly, shaking the ground. The rover went out to make sure
things were "holding together" from the day's repairs. He found nothing amiss,
though the clapper was slamming and shaking the ground so violently that people
in Delta Junction thought they were hearing the explosion of artillery shells at
a nearby military Fort Greely.
An hour later, moving oil reached the station and the crew started the
pumps. During the restart, the booster pump for the suction line - a 10-inch
line that transfers oil from the pump station's 55,000-barrel relief tank back
into the mainline - was damaged.
Inspectors found that the actuator that drives the booster suction valve -
a unit so large that it takes two men to lift it - ripped out of its four-bolt
mounting and came to rest against the bolts of an adjacent flange, its housing
cracked from the pounding it took from the yard check's slamming.
Fortunately, on that day, nothing else went wrong while the pump and the
lines carrying oil in and out of the relief tank were out of commission.
A Near-Disaster at Pump Station 8
What could go wrong was best exemplified during Alyeska's May 6, 1996 shutdown.
Problems began when the oil flow from Prudhoe Bay reached Pump Station 8, just
south of Fairbanks.
Both seals on a mainline pump failed. With oil leaking at the pump house,
the crew moved to isolate the pumphouse from oil flow. The isolation valves
failed and oil continued to flow into the pump station. The start-up turned into
a near-disaster, with spilled crude and heavy smoke filling the pump building.
Alyeska investigators later determined that the OCC turned on the mainline
pump too soon. There wasn't enough pressure to start the pump which overheated
and suffered a "catastrophic failure." Oil continued to flow into the overheated
pump for 15 minutes.
To bring Pump Station 8 back on line and deal with another leaking valve
at Pump Station 4, the northern portion of the line was shut down again.
On the downslope of the Brooks Range, pressure inside the 48-inch pipe can
build to dangerous levels. To relieve that pressure, the tank at Pump Station 5
was built with three times the capacity of relief tanks at other stations. But
with PS#5's relief tank was out of commission for repairs, Alyeska planned to
divert oil to the smaller relief tanks at stations 6, 7 and 8.
There was a flaw in this plan: At that time, PS7 had been out of service
for almost a year and PS#8 was still standing down from the morning's near-
disaster. Only the smaller tank at PS#6 was available to take the place of PS5's
large tank.
In May 1996, Alyeska took the 150,000 barrel pressure relief tanks at Pump
Station 5 out of service for maintenance. PS5 was returned to operation without
the requisite inspection and flow testing to ensure the new piping could handle
a surge of oil from the pipeline.
Inspection and testing were scheduled for August 29, 1996, four weeks
after PS5 had returned to service, but the test was canceled when the inspection
revealed that a key pipe support and the large bolts that held a critical clamp
in place did not meet specification. Engineers reportedly feared that the surge
of oil might rip the system apart. The tests were rescheduled for the following
month. During the second test, a hydraulic fluid leak in a key valve resulted in
the system being placed in service on an "interim" basis - without a complete
test.
A History of Spills and Fires
Shutdowns are not the only indicator of potentially serious problems. The range
of mishaps that occurred during the operation of TAPS in 1994 and 1995 includes
seven fires , a 2,800-gallon propane leak at a remote gate valve, a 7,100-gallon
spill of sodium hydroxide. and Freon leaks from buried lines that keep the
foundations of northern facilities frozen.
During 1994 and 1995, potentially serious incidents threatening workers,
civilians and the environment included: 9 crude oil spills; 14 other spills; 7
fires; 25 shutdowns or slowdowns due to communication failures; 6 incidents that
caused flow reductions; 20 leaks in the Vapor Recovery System piping at the
Valdez terminal and four other potentially serious incidents.
Electric cables provide power, control and communications for more than a
dozen pump stations and key facilities. Hydrocarbon vapors and electrical sparks
can combine to cause fires and explosions. An explosion on TAPS could be
catastrophic, endangering lives, property and wilderness.
A 1993 BLM audit conducted by Quality Technology Co., an independent
auditor, confirmed a wide range of electrical problems. "The greatest hardware
threats to the health and safety of the public and environment," the auditor
observed, "relate to the electrical systems."
Overloaded cable trays were the most significant problem. Cable trays are
open-topped metal baskets or frames that carry wires to equipment, or hook into
other wires. At numerous locations, the auditors observed wires spilling out of
overloaded cable trays. In many places the cable trays were inadequately mounted
or hung, posing a threat that they could come loose, causing cable breakage.
Subsequent inspections found hazards that included improperly mixed wires,
poorly grounded equipment, improperly installed and overloaded junction boxes.
Electrical problems caused two of the seven fires reported in 1994 and 1995.
Apart from fires and explosions, electrical failures can prevent pipeline
operators from shutting down the pipeline or diverting oil to relief tanks to
minimize spills.
Inspectors identified, 48,110 items as failing Alyeska's electrical code.
Some 17,000 of the electrical deficiencies were simple "housekeeping" items -
i.e., missing screws on cover plates or loose grounding connections. That left
more than 31,000 major electrical problems still to be dealt with.
Near Disaster at Thompson Pass
Fearing that the pipeline was leaking at Thompson Pass, 27 miles from Valdez,
Alyeska mobilized for a major spill response in late November of 1996. Vapor
bubbles had been building up in the pipeline on steep descent from Thompson Pass
causing a section of the pipeline to begin bouncing vigorously.
Alyeska's government watchdogs later said the bubble phenomenon was well-
known. How, then, could the shaking have gone unnoticed by the pipeline
operators until residents below phoned in to complain that the earthquake-like
shocks coming from the pipeline were waking them up at night?
More perplexing is the four-month delay between the first report on July
25 that the Thompson Pass pipeline was bouncing around and Alyeska's energetic
response to a potential oil spill in late November. The cannon-like thumping was
strongest near major dents in the pipeline. Such dents can significantly weaken
the line. Recognizing this weakness, Alyeska had already put at least six
reinforcement sleeves over the line in the five-mile stretch between the lower
portion of Thompson Pass and Keystone Canyon.
On Nov. 18, Alyeska's engineers reported serious concerns about pipeline
strength near the major dents 20 miles out of Valdez. On November 26, Alyeska
sent crews up the steep snow-bound slope of Thompson Pass to install soil gas
probes near the site of bubble explosions within the pipe. Two days later, when
the probe sniffed hydrocarbon fumes, Alyeska initiated its spill response plan.
When it turned out to be a false alarm, there was a headlong rush to
praise Alyeska's vigorous spill-response preparations. Alyeska's eventual
response did represent improvement over past performance. But if probes been
installed back in September, it would not have been necessary to construct a
winter road to haul a drill rig onto the steep side of Thompson Pass to
investigate a possible leak.
In 1995 Alyeska began installing a more sophisticated small-leak detection
system. The new system was supposed to provide near-instantaneous feedback from
the line and locate the approximate source of a leak. Unfortunately, a spill
often had to be larger than 2,500 barrels per day to trigger the alarm. The new
system, like the old one, issues frequent false alarms.
When Gate Valves Fail
Unplanned RGV closures could cause over-pressuring of the line if upstream pumps
continue to push oil downstream towards an unintentionally closed valve.
While accidental full closures have been rare, one occurred in 1982 and
another in 1992. The latter, caused by a ground fault in an electrical conduit,
resulted in a 131-percent over-pressuring of the pipeline in the hills north of
Fairbanks.
Of all the RGV's installed in TAPS, perhaps the most critical ones are
those on the steep south flank of the Brooks Range. After the oil crests Atigun
Pass, the line drops 3,600 feet over the next 100 miles to Pump Station 5.
Pressure inside the pipe can build to dangerous levels. Pump Station 5 was built
to relieve this pressure by diverting oil to its 150,000 barrel storage tanks -
three times the relief capacity at a typical TAPS pump station.
Because an emergency at PS5 could not wait for response from Valdez, a
special computer link was installed between Pump Stations 4 and 5 to
automatically shut down the pumps in Station 4 and close remote valves if
Station 5 shuts down. But the automatic shut down system only works if the
remote computer linkage works. According to TAPS records, 11 of 22 RGV
communication problems reported in 1994 and 1995 involved this critical region
on the south side of Atigun Pass.
In August 1994, Alyeska disabled all 16 RGVs normally controlled through
Pump Station #4 to work on the radio link to the valves. With radio maintenance
completed, a two-person crew was assigned to visit each site by helicopter to
reactivate the RGV control systems. At RGV #9 ,overlooking the Middle Fork of
the Koyukuk River, the maintenance crew restored power without realizing that
they had left the manual switch that closes the valve in the "on" position.
With a storm brewing and their helicopter running low on fuel, the workers
were in a hurry to complete their mission. They had already headed for the next
valve down the line when OCC ordered them back because RGV #39 appeared to be
closing.
By the time they landed and re-set the switches, the valve had moved 76
percent of the way toward full closure. Before that week-end was out, the worst
storms in memory hit the Brooks Range, closing roads paralleling the pipeline.
Any spill response relying on overland transportation would have been seriously
crippled.
RGV problems are by no means limited to the critical south slope of the
Brooks Range. Another problematic site is Thompson Pass, where the begins a
steep descent to Valdez - 27 miles away. One RGV in this critical area
registered 86 communication failures in 1994. At various times since 1992, when
communications between Valdez and the RGVs has broken down, Alyeska has had to
dispatch field staff by truck or helicopter to see whether valves are open or
closed. The workers must sit at the valve site with a two-way radio until
communications can be re-established.
Government Oversight and the JPO
Alyeska promised to protect the 800-mile corridor and surrounding lands with the
safest delivery system possible, but during the pipeline's construction, the
discovery of falsified welding certificates brought TAPS into national headlines
but after construction was finished, the government's monitoring efforts
languished. During the 1980s , a Government Accounting Office report concluded,
government monitors simply allowed Alyeska to police itself. Following Alyeska's
delayed response to the 1989 Exxon Valdez spill, quality control inspector
complaints and congressional inquiries led to a revitalizaton of virtually
moribund TAPS monitoring efforts.
In 1990, federal Bureau of Land Management (BLM) and Alaska's State
Pipeline Coordinator's Office (SPCO) established the Joint Pipeline Office (JPO)
- a collaborative effort of 11 state and federal agencies that is responsible
for monitoring Alyeska's management of the pipeline.
The cold truth is that regulatory action is subject to the pressures of
the political system. With government officials understandably loath to turn off
the spigot that controls nearly one-tenth of the country's oil, JPO's main
function has been to officially endorse Alyeka's operations - even when agency
documents indicate problems with these same operations.
Alaska's State Pipeline Coordinator has admitted that he would be unlikely
to shut down TAPS without the direct concurrence of the Alaska Commissioner of
Natural Resources and the Alaska Director of the federal Bureau of Land
Management. For political and economic reasons, a shutdown of TAPS without the
expressed consent of the Governor of Alaska and high-ranking federal officials
is highly improbable.
Concerns Remain Unaddressed
Public criticism of the JPO has come primarily from two quarters: The
Alaska Forum for Environmental Responsibility (AFER) and Billie Pirner Garde, a
whistleblower attorney and AFER counsel. AFER representatives have expressed the
following principal concerns about the government monitoring effort:
- Slow identification of significant TAPS problems;
- Lack of stringency when Alyeska misses deadlines or fails to meet goals
specified by monitors;
- Slow response to issues raised by whistleblowers and inability to
resolve harassment issues;
- JPO's failure to publicly censure Alyeska
JPO deserves credit for re-inventing the TAPS oversight organization to
deal with the challenge of ensuring safe oil transport across Alaska. But
increased staff, greater funding, new programs and huge volumes of technical
paperwork do not, in and of themselves, guarantee effective oversight.
With Alaska's North Slope set to pump oil for decades to come, it becomes
increasingly important that TAPS is maintained in top-flight condition. It is
difficult to imagine how Alyeska can accomplish this while the company continues
to cut operating costs. Yet that's exactly what Alyeska managers are now asking
their employees to do.
It is imperative for the President to order an independent task force to
evaluate the condition of the pipeline and Alyeska's capability to transport oil
across Alaska without causing undue risk to the environment and the nation's oil
supply. Congress mandated that review in 1990 but never funded it. In 1996, the
JPO said an external review was planned for 1997. To date, it has not
materialized.
Without an independent, in-depth review of TAPS operations and government
oversight efforts, TAPS will remain a Pipeline in Peril.
Sidebar: Spill Plans: Reconsidered or Just Re-drawn
Sidebar: Sounding TAPS for Competition
Sidebar: Sounding TAPS for the Wild
Richard A. Fineberg has worked as a policy analyst in the Alaska Office of
Management and Budget and has served as an advisor to the governor on oil and
gas policy. His freelance reporting has appeared in The Nation, The New Republic
and the Anchorage Daily News. This report was excerpted from Pipeline in Peril
which is available from the Alaska Forum for Environmental Responsibility, PO
Box 188, Valdez, AK 99686, (907) 835-5460, fax: (907) 835-5410,
www.alaska.net/~afervdz.html